The construction of a new Vietnam-Singapore industrial park kicked off in northern Vietnam’s Lang Son Province on Friday, making the facility the 16th of its kind in the country so far.

The Lang Son administration and the Vietnam Singapore Industrial Park and Township Development Joint Stock Company (VSIP JSC) conducted a groundbreaking ceremony for the VSIP Lang Son project in the province’s Huu Lung District.
Located in an area of nearly 600 hectares, the project is expected to cost over VND6,361 billion (US$250 million), of which the investor VSIP JSC contributes over VND954 billion ($37.5 million), according to the Vietnam News Agency.
The project will be developed through three phases, with phase 1 covering 200 hectares and anticipated to come into operation by the third quarter of 2025.

Phases 2 and 3, to be developed in the remaining area, are scheduled to be completed in September 2026 and September 2027, respectively.
When all the three phases are operational, the new industrial park is expected to generate about 40,000 jobs, including those for youths and people of ethnic minorities in Lang Son.
Chairman of the provincial People’s Committee Ho Tien Thieu emphasized that the industrial sector has long been determined as the driving force of the local economic growth and development.
Thieu requested that all relevant agencies create the most possible favorable conditions for the project’s investors to speed up the construction progress.
The province’s leader also asked the investors, consulting units, and contractors of the project to strictly comply with relevant regulations and standards to ensure construction quality and industrial safety and hygiene.
He directed Huu Lung District authorities to accelerate site clearance and support residents subject to relocation due to the project through effectively applying related policies and regimes.
The leader also called on involved local people to support the implementation of the project through handing land over to the investor timely and smoothly.
Speaking at the ceremony, Singaporean Ambassador to Vietnam Jaya Ratnam emphasized that Vietnam-Singapore industrial parks serve as a symbol of the fruitful bilateral relations between the two countries.
The expansion of the chain of VSIPs in Vietnam is unprecedented in recent years, reflecting not only the strong interest of foreign investors in the country but also the success of the Vietnamese government in its efforts to create an increasingly favorable investment environment.
The ambassador expressed his hope that VSIP Lang Son will play a central role in encouraging and facilitating high-quality investments from Singapore, especially in infrastructure development, supply chain services and logistics, green economy, farm produce processing.
The Singapore Business Federation will work with the provincial authorities to explore opportunities for Singaporean investors in these areas, he added.
The project has passed the “contract award announcement” milestone and has officially broken ground, marking the transition from information disclosure to active execution.
Thursday, 15 Jan, 2026
The Hung Phu 2 Social Housing Project in Nha Trang broke ground on January 9, 2026, with progress reaffirmed by an update on January 14, 2026. With a scale of 30 above-ground floors, one basement level, 1,062 apartments, and a total investment exceeding VND 1.445 trillion, this is a large-scale project capable of generating a long B2B demand chain from construction through to finishing.
Thursday, 15 Jan, 2026
The Hanosimex Mixed-Use Building project in Minh Khai officially broke ground on January 10, 2026. For office-related developments, the key priority for B2B players is to quickly identify the investor, design consultant, and early-stage contractors in order to align with the project’s execution rhythm from the outset.
Thursday, 15 Jan, 2026
FIT Foxconn Nghe An Phase 3 at WHA Industrial Zone 1 is an electronics manufacturing project with clearly defined output specifications and designed capacity detailed in the project file. When “output” is specified at this level, B2B service providers should approach the project with solutions directly aligned to production scale, operational standards, and the execution rhythm based on the identified main contractor and construction parties.
Thursday, 15 Jan, 2026
The King Point Vietnam factory at VSIP II A officially broke ground on January 7, 2026, with an update indicating a groundbreaking ceremony on January 12, 2026. As a manufacturing project focused on small mechanical products such as rivets, bolts, and screws, this type of factory typically prioritizes stability, standardization, and a clearly defined implementation schedule from the early stages.
Thursday, 15 Jan, 2026
On the morning of January 7, 2026, the Quang Ninh Provincial Economic Zone Authority granted the Investment Registration Certificate for the project. The investor is Nature Health Development International Co., Ltd., headquartered in Hong Kong, China. The project is considered a concrete follow-up to Quang Ninh Province’s investment promotion mission to Shanghai and Suzhou in mid-December 2025.
Thursday, 15 Jan, 2026